• OPENING 2019

  • Furr Elementary - Westridge Site

    Elementary #10

    Location: This campus will be located in McKinney in the Valor Pointe neighborhood off of Bluestem Road.

    Work Completed and Ongoing - as of February 2019
    Storm Shelter:
    • Continue damp proofing, sealing and caulking interior
    • Poured slab top of shelter – End of January
    • Installing lintels for brick and louvers
    • Fine grading / prepping for floor slab
    Area 4:
    • (Overhead) Duct work insulation and plumbing insulation
    Electrical:
    • Continue masonry above roof at Storm Shelter
    • Installation of IDF computer rack
    • Started two siding gypsum board at Administration
    Area 3:
    • Continue interior metal stud framing
    • Duct work and Roof curbs
    • Electrical over head
    Area 2:
    • Metal stud framing
    • Scheduling for structural steel inspection
    • Duct hangers and AC roof curbs
    Area 1:
    • Continue misc. steel at expansion joint
    • Metal deck welded

    Work Upcoming (Two Week Look Ahead)
    • Continue roofing – Areas 2 and 3
    • Continue work clerestory
    • Misc. steel / metal deck inspection – Area 1
    • Framing / electric inspection – Area 3
    • Exterior masonry

  • Stuber Elementary - Legacy Site

    Elementary #11

    Location: This campus will be located in Prosper in the Parks of Legacy neighborhood off of Fishtrap Road.

    Work Completed and Ongoing - as of February 2019
    • ICF complete – Area 2, 3 and 4
    • Started ICF – Area 1
    • Continue structural steel – Area 2, 3 and 4
    • Continue HVAC duct work – Area 4
    • Continue overhead electrical and plumbing – Area 4
    • Started fire sprinkler piping
    • Continue CMU at corbels for roofing through wall
    • Installed rip rap at outfalls
    • Grading for sidewalks east side

    Work Upcoming (Two Week Look Ahead)
    • Complete ICF – Area 1
    • Start CMU in kitchen
    • Start exterior stone / brick veneer
    • Complete structural steel – Area 4
    • Start structural steel – Area 1
    • Start roofing – Area 4

  • Bill Hays Middle School

    Hays Middle School

    Location: This campus will be located in Frisco south of Rock Hill Road on the west side of Hillcrest Rd.

    Work Completed and Ongoing - as of February 2019
    • Terrazzo Flooring Area 4
    • Ceiling Tile Cafeteria Area 4
    • Pogue’s Punch List Areas 2 South and 3
    • Instrument Cabinets
    • Basketball Goals at Storm Shelter Area 7 North
    • Scoreboards at Gym Area 7 North
    • Ceiling Tile Area 7
    • Doors and Hardware Area 7 North
    • Millwork Area 7

    Work Upcoming (Two Week Look Ahead)
    • Kitchen Revisions Area 4
    • Resinous Flooring Area 6
    • MEP at Storm Shelter Area 7 North
    • Concession and Storage Buildings
    • Irrigation and Landscaping
    • Site Grading and Miscellaneous Site Concrete
    • Synthetic Turf at Field and Surfacing at Tennis Courts

  • PISD Stadium

    PISD Stadium

     

    Live Feed

     

     

     

     

    Location: The 12,000-seat stadium will be located on the same property as Frontier Park on the west side of the railroad tracks on the south side of Frontier Parkway. 

    Site work
    • Poured site work grade beams front of B and SW area
    • Continue masonry at field wall
    • GCEC- install wire at soccer fields
    • Continue irrigation
    • Started foundation at lift station

    Field House
    • Continue tile work
    • Installing low voltage
    • Glazing continues
    • Closing interior walls

    Home side
    • Continue steel erection
    • Continue exterior framing
    • Started scaffolding and wall framing field side
    • Roofed SW restroom
    • Continue fireproofing
    • Begin window sill framing press box
    • Continue brick at concession
    • Continue masonry towers south side
    • Continue lower bowl steps

    Visitor side
    • Poured Slab on Metal Deck
    • Continue masonry at towers and ticket booths
    • Begin erection of steel towers

  • PISD Natatorium

    PISD Natatorium

    Location: The natatorium will be adjacent to the new stadium next to Frontier Park.

    Building
    • Installing plumbing fixtures west area
    • Continue fire suppression system
    • Continue roofing and fascia
    • Install Interior Storefronts South area
    • Start tile south restrooms
    • Final paint west area
    • Fire alarm installation
    • Data and access control install
    • Delivery and install of pool PDU unit

    Pool
    • Start grading warm up pool
    • Backfill gravel at competition pool


    Site
    • Cut and form sidewalks

  •  

    OPENING 2020

  • Rock Hill High School

    Rock Hill High School

     

    Live Feed

     

     

     

     

    Location: This campus will be located on Coit Road south of 380.

    Work in Progress or Ongoing
    • Grade Beams ongoing – Areas E and T
    • Fire lane pour north of property connecting to Hardy Drive
    • Slabs ongoing in – Areas D, N and U
    • Pour curbs connecting Hardy to Coit Road
    • CoServ conduit installation ongoing, working on lines adjacent to Hardy Drive
    • Roof decking ongoing – Area A
    • 2nd floor slab completed – Area A
    • Fireproofing Ongoing – Area A
    • Steel erection – Area B
    • Steel erection on MAC Building Ongoing – Area S
    • Complete liming on all remaining fire lanes and parking lots
    • Batting cage slabs poured


    Work Upcoming (Two week look ahead)
    • All remaining fire lanes and paving to be completed
    • Retaining wall formed and poured after acceptance by Architect
    • Grade beams – Building F
    • Second floor decking – Area B
    • Second floor pour to be complete – Area B
    • Steel erection – Area C and U
    • Slab Pours – Area D and N

  •  

     

  • Furr Elementary - Photo Gallery

  •  

     

  •  

     

  •  

     

  •  

     

  • Stuber Elementary - Photo Gallery

  •  

     

  • Hays Middle School - Photo Gallery

  •  

     

  • PISD Stadium - Photo Gallery

  •  

     

  •  

     

  •  

     

  • Natatorium - Photo Gallery

  •  

     

  •  

     

  •  

     

  • Rock Hill High School - Photo Gallery