• OPENING 2019

  • Elementary #10 - Westridge Site

    Elementary #10

    Location: This campus will be located in McKinney in the Valor Pointe neighborhood off of Bluestem Road.

    Work Completed and Ongoing - as of October 2018
    • Testing lab continuing with density at grade beams
    • Grading of fire lanes on south side
    • Installing lime at north fire lane
    • All lime test densities, depth, gradations have passed on north parking lot and approaches
    • Hauling off extra dirt
    • Co-serve setting junction box in the 25 ft. easement
    • Installation of carton forms and rebar continues – Area 4
    • Grading and prepping ongoing – Area 3
    • Installation of underground electric ongoing – Area 2

    Work Upcoming (Two Week Look Ahead)
    • Pour slab – Area 4
    • Pour portion of slab – Area 3
    • Pour north parking, Northwest and northeast approaches
    • Continue with lime at south fire lane and parking

  • Elementary #11 - Legacy Site

    Elementary #11

    Location: This campus will be located in Prosper in the Parks of Legacy neighborhood off of Fishtrap Road.

    Work Completed and Ongoing - as of October 2018
    • Regraded fire lanes and paving west side ready for lime
    • Started liming west side fire lanes and parking
    • Installed RCP for off site area drain
    • Installed 20” water line
    • Taken water samples for water loop
    • Continue tying pier rebar
    • Continue drilling piers – Area 2
    • Formed and poured grade beams – Area 4
    • Start digging grade beams and pilasters – Area 3

    Work Upcoming (Two Week Look Ahead)
    • Start fine grading for paving areas east side
    • Start sleeves for paving areas east side
    • Start liming paving areas east side
    • Continue drilling piers
    • Start underground electric – Area 4
    • Start plumbing underground – Area 4
    • Test chemical injection – Areas 1 and 2
    • Start utilities for RFP2
    • Start grading for RFP2
    • Start form work and rebar for paving

  • Bill Hays Middle School

    Hays Middle School

    Location: This campus will be located in Frisco south of Rock Hill Road on the west side of Hillcrest Rd.

    Work Completed and Ongoing - as of October 2018
    • Installation of Visual display boards – Areas 1, 2 and 8
    • Off-site paving of Alveria, Aragon and Hillcrest
    • Doors and Hardware – Areas 1, 2, 3 and 8
    • Toilet partitions – Area 1 and 3
    • Metal wall studs and gypsum board – Area 4
    • Concrete roof – Area 7 (Shelter)
    • Sunshades – Areas 1, 2, 3 and 8
    • MEP rough-in – Area 4

    Work Upcoming (Two Week Look Ahead)
    • Electrical trim – Area 8
    • Metal roofing at clearstory – Area 4
    • Tape, Bed, and Texture and Paint – Area 5
    • Interior Masonry at Storm Shelter – Area 7 North
    • Concession and storage building
    • Doors and Hardware – Areas 2, 3 and 8

  • PISD Stadium

    PISD Stadium

     

    Live Feed

     

     

     

     

    Location: The 12,000-seat stadium will be located on the same property as Frontier Park on the west side of the railroad tracks on the south side of Frontier Parkway. 

    Site work:
    • Chemical injection at field

    Area B (Community Room):
    • Complete exterior framing
    • Complete dry in of roof
    • Continue exterior masonry
    • Continue interior overhead MEP

    Home side:
    • Continue erection of press box
    • Pour slab over metal deck (Area D2) concourse and restroom
    • Continue slab over metal deck – Area A
    • Begin masonry veneer on south ticket booth

    Visitor side:
    • Continue foundation – Area C
    • Pour concrete columns this week
    • Underground storm line on south end

    Milestone: Permanent power connection

  • PISD Natatorium

    PISD Natatorium

    Location: The natatorium will be adjacent to the new stadium next to Frontier Park.

    Building:
    • Continue masonry at south and east area
    • Continue plumbing top out
    • Begin roof decking
    • Continue electrical rough-in
    • Form and pour bleachers

    Pool:
    • Begin grading/preparation for 2nd half of competition pool foundation

  •  

    OPENING 2020

  • Rock Hill High School

    Rock Hill High School

     

    Live Feed

     

     

     

     

    Location: This campus will be located on Coit Road south of 380.

    Work in Progress or Ongoing
    • Piers – Areas L, J and H
    • Grade Beams ongoing
    • Lime of South and East Fire Lane
    • Lime of East Parking Lot
    • Underground plumbing and electrical work – Areas B, C and N
    • Site utilities ongoing. Will be complete in next two weeks
    • Electrical and Irrigation sleeve installation


    Work Upcoming (Two week look ahead)
    • Multi-Purpose Facility (MPF) piers
    • Slab pour – Area A
    • Pour East Parking Lot
    • East and South Fire Lanes
    • Out Building Piers

  •  

     

  • Elementary #10 - October 2018

    Elementary #10

    Elementary #10

    Elementary #10

  • Elementary #11 - October 2018

    Elementary #11

    Elementary #11

    Elementary #11

  • Hays Middle School - October 2018

    Hays Middle School

    Hays Middle School

    Hays Middle School

  • PISD Stadium - October 2018

    PISD Stadium

    PISD Stadium

    PISD Stadium

  • PISD Natatorium - October 2018

    PISD Natatorium

    PISD Natatorium

  • Rock Hill High School - October 2018

    Rock Hill High School

    Rock Hill High School

    Rock Hill High School